Report 3 (Williamson): Building Remedial Report

The third monthly report from John Williamson Inc., dated 6 January 2012. It notes the unexpected discovery of concrete topping on two balconies, and that the same is expected to be found on three more balconies. Also of interest is that moisture probe testing on the north-east wall has been completed, and a report is […]

Posted on January 24, 2012 at 10:23 by Admin · Permalink · Comments Closed
In: Construction, Updated posts · Tagged with: , , , , , , ,

Report 2 (Williamson): Building Remedial Report

The second monthly report from John Williamson Inc., dated 6 December 2011. This report notes that work has started on the south side of the building. Attached to the report is a Christmas card with the note that there will be no construction work performed between 23 December and 3 January.

Posted on January 24, 2012 at 09:54 by Admin · Permalink · Comments Closed
In: Construction · Tagged with: , ,

Report 1 (Williamson): Building Remedial Report

Yesterday (8 November) Strataco emailed a copy (dated 3 November) of what I assume is the first of the monthly reports promised by John Williamson Inc. I presume that hard copies were also distributed yesterday to those who have not chosen to receive them via email. Reference is made in the report to the schedule […]