Report 3 (Williamson): Building Remedial Report
The third monthly report from John Williamson Inc., dated 6 January 2012. It notes the unexpected discovery of concrete topping on two balconies, and that the same is expected to be found on three more balconies. Also of interest is that moisture probe testing on the north-east wall has been completed, and a report is […]
In: Construction, Updated posts · Tagged with: building repair, council meetings, decks, john williamson inc., president, special general meetings, strata council, williamson reports
Report 2 (Williamson): Building Remedial Report
The second monthly report from John Williamson Inc., dated 6 December 2011. This report notes that work has started on the south side of the building. Attached to the report is a Christmas card with the note that there will be no construction work performed between 23 December and 3 January.
In: Construction · Tagged with: building repair, john williamson inc., williamson reports
Notification 2 (New City): Project Start
Delivered as I was posting the picture of the scaffolding is a letter from New City Contracting dated today with the subject “Notification #02 — Project Start”. It’s addressed to residents in units “101-108- 201- 208- 301- 308- 401- 406” (actual punctuation and spacing). I’m not sure if that means it has been delivered to […]
In: Construction · Tagged with: building repair, documents, new city contracting, notice board
More scaffolding has arrived
In other breaking news, a bunch of scaffolding was unloaded into the common area on the south side of the building this afternoon. By the way, does anyone in 202, 203, 302 or 303 have any comments on the application of deck membrane on their decks that has presumably happened by now?
In: Construction · Tagged with: building repair, deck membrane, decks
Notice 4 (Williamson): Balcony deck membrane
The latest notice from John Williamson Inc., dated 17 November, advises that the application of liquid deck membrane to the decks of units 202, 203, 302 and 303 will begin “immediately”. Emphasis is placed on the fact that this stuff doesn’t smell particularly good, but that the smell should dissipate within twenty-four hours and that […]
In: Construction · Tagged with: building repair, deck membrane, decks, john williamson inc., smells, williamson notices
Notice 3 (Williamson): Remembrance Day holiday
I’m a little late in posting this, but notice number 3 (dated 10 November) from John Willimason Inc. informs us of the fact that Friday, 11 November (Remembrance Day) was a holiday, and no work was conducted on that date.
In: Construction · Tagged with: building repair, john williamson inc., williamson notices
Report 1 (Williamson): Building Remedial Report
Yesterday (8 November) Strataco emailed a copy (dated 3 November) of what I assume is the first of the monthly reports promised by John Williamson Inc. I presume that hard copies were also distributed yesterday to those who have not chosen to receive them via email. Reference is made in the report to the schedule […]
In: Construction, Updated posts · Tagged with: building repair, john williamson inc., new city contracting, notice board, strataco management, williamson reports
Clarification from EXP on their earlier Additional Investigations Report
On Wednesday, 26 October, Strataco delivered a package containing the following to the door: A 1-page cover letter from the Strata Corporation dated 24 October 2011 and signed by Kim Sheldon, Strata Council President, A 15-page Additional Investigations Report — Building Envelope report from EXP dated 29 September 2011, Copies of this were already given […]
In: Construction · Tagged with: building repair, documents, dubas engineering, engineering reports, exp services, president, rdh building engineering, strata council, strataco management, trow associates
Notice 2 (Williamson): Updated construction start date
Notice number 2 from John Williamson posted on the notice board by the elevator on the parkade level on Tuesday, 18 October (and dated the same day) indicates that equipment will start to be mobilised on site on Monday, 24 October, with actual construction (actually, demolition) work to start on the following Monday, 31 October, […]
In: Construction · Tagged with: building repair, john williamson inc., williamson notices
Notice 1 (Williamson): Construction start date
According to a notice from John Williamson posted yesterday (9 October, but dated 5 October) on the notice board by the elevator on the parking level, New City is set to start construction on 31 October. This would imply that New City has now officially been selected as the contractor, although I don’t recall that […]
In: Construction, Updated posts · Tagged with: building repair, john williamson inc., new city contracting, williamson notices