Report 3 (Williamson): Building Remedial Report

The third monthly report from John Williamson Inc., dated 6 January 2012. It notes the unexpected discovery of concrete topping on two balconies, and that the same is expected to be found on three more balconies. Also of interest is that moisture probe testing on the north-east wall has been completed, and a report is […]

Posted on January 24, 2012 at 10:23 by Admin · Permalink · Comments Closed
In: Construction, Updated posts · Tagged with: , , , , , , ,

Report 2 (Williamson): Building Remedial Report

The second monthly report from John Williamson Inc., dated 6 December 2011. This report notes that work has started on the south side of the building. Attached to the report is a Christmas card with the note that there will be no construction work performed between 23 December and 3 January.

Posted on January 24, 2012 at 09:54 by Admin · Permalink · Comments Closed
In: Construction · Tagged with: , ,

Notice 4 (Williamson): Balcony deck membrane

The latest notice from John Williamson Inc., dated 17 November, advises that the application of liquid deck membrane to the decks of units 202, 203, 302 and 303 will begin “immediately”. Emphasis is placed on the fact that this stuff doesn’t smell particularly good, but that the smell should dissipate within twenty-four hours and that […]

Posted on November 19, 2011 at 03:59 by CraigH · Permalink · Comments Closed
In: Construction · Tagged with: , , , , ,

Notice 3 (Williamson): Remembrance Day holiday

I’m a little late in posting this, but notice number 3 (dated 10 November) from John Willimason Inc. informs us of the fact that Friday, 11 November (Remembrance Day) was a holiday, and no work was conducted on that date.

Posted on November 12, 2011 at 21:16 by CraigH · Permalink · Comments Closed
In: Construction · Tagged with: , ,

Report 1 (Williamson): Building Remedial Report

Yesterday (8 November) Strataco emailed a copy (dated 3 November) of what I assume is the first of the monthly reports promised by John Williamson Inc. I presume that hard copies were also distributed yesterday to those who have not chosen to receive them via email. Reference is made in the report to the schedule […]

Uploaded more documents

In keeping with the goals of this website, I have uploaded some more documents so that they’re easily available for all Owners and residents. Unfortunately, because they’re all scans, they are not searchable because they are essentially images, not text documents. I would hope and expect that as this website grows and improves, such documents […]

Posted on October 20, 2011 at 05:22 by CraigH · Permalink · Comments Closed
In: Administration · Tagged with: , , ,

Notice 2 (Williamson): Updated construction start date

Notice number 2 from John Williamson posted on the notice board by the elevator on the parkade level on Tuesday, 18 October (and dated the same day) indicates that equipment will start to be mobilised on site on Monday, 24 October, with actual construction (actually, demolition) work to start on the following Monday, 31 October, […]

Posted on October 20, 2011 at 02:55 by CraigH · Permalink · Comments Closed
In: Construction · Tagged with: , ,

Notice 1 (Williamson): Construction start date

According to a notice from John Williamson posted yesterday (9 October, but dated 5 October) on the notice board by the elevator on the parking level, New City is set to start construction on 31 October. This would imply that New City has now officially been selected as the contractor, although I don’t recall that […]

Posted on October 10, 2011 at 12:16 by CraigH · Permalink · Comments Closed
In: Construction, Updated posts · Tagged with: , , ,

Possible power surges during construction

I contacted John Williamson with respect to his caution about possible power surges during construction. He clarified that the possibility of a power surge in a suite would only be present during work on that suite’s balcony or deck. This is not something that is a possibility building-wide for the duration of the construction. He […]

Posted on October 9, 2011 at 09:06 by CraigH · Permalink · Comments Closed
In: Construction · Tagged with: ,

Construction budget passed

Now that the construction budget has been passed and much of the control of the project has been given to project manager John Williamson, I’m actually feeling a little more confident about how things will progress from here on. If nothing else, he has committed to monthly reports, so at least we’ll know what’s going […]

Posted on September 30, 2011 at 07:09 by Admin · Permalink · Comments Closed
In: Construction · Tagged with: , ,