Added and reorganised documents
I’ve been busy scanning a whole bunch of documents and adding them to the Documents page. Besides the fact that I have uploaded a copy of every digital document I already have, there isn’t really any logic to what is there and what isn’t; I haven’t picked a specific date and uploaded everything sent out since […]
In: Administration · Tagged with: documents, strataco management
Report 1 (Williamson): Building Remedial Report
Yesterday (8 November) Strataco emailed a copy (dated 3 November) of what I assume is the first of the monthly reports promised by John Williamson Inc. I presume that hard copies were also distributed yesterday to those who have not chosen to receive them via email. Reference is made in the report to the schedule […]
In: Construction, Updated posts · Tagged with: building repair, john williamson inc., new city contracting, notice board, strataco management, williamson reports
How to enforce by-laws and rules
Back to our regularly-scheduled programming. One of the things I want to do on this website is highlight some of the excellent instruction guides on the Financial Institutions Commission website and how they apply to Trinity Place at the moment. There are 28 of these guides, and given the nonsense surrounding the petty removal of […]
In: Governance · Tagged with: anonymous sign stealer, by-laws, free speech, legal, notice board, rdh building engineering, rules, strata council, strataco management
Anonymous strikes again!
I’m all in favour of dissent. Really! Even if I wasn’t, I’ve written nothing on this website that would indicate that I don’t tolerate other points of view. But I can’t debate with a shadow, and in this case the shadow is the anonymous person that has a bee in his or her bonnet about […]
In: Administration · Tagged with: anonymous sign stealer, by-laws, free speech, legal, notice board, rules, strata council, strataco management
Clarification from EXP on their earlier Additional Investigations Report
On Wednesday, 26 October, Strataco delivered a package containing the following to the door: A 1-page cover letter from the Strata Corporation dated 24 October 2011 and signed by Kim Sheldon, Strata Council President, A 15-page Additional Investigations Report — Building Envelope report from EXP dated 29 September 2011, Copies of this were already given […]
In: Construction · Tagged with: building repair, documents, dubas engineering, engineering reports, exp services, president, rdh building engineering, strata council, strataco management, trow associates
Website notice on notice board
Twice in the last three weeks or so since this website was set up, someone has removed the small notice I have place on the notice board in the parkade vestibule by the elevator. Today there was a handwritten notice in its place which read as follows: PLEASE NOTE THAT THIS NOTICE BOARD IS RESERVED […]
In: Administration, Updated posts · Tagged with: anonymous sign stealer, by-laws, free speech, legal, notice board, rules, strataco management
Emergency plumbing work
It seems that a leak was reported in the *01 and/or *02 stacks yesterday (Friday, 30 September). Artisan Plumbing & Heating Ltd. were called in and the leaks was eventually isolated to a split pipe (if I understood correctly) in the wall between units 401 and 402. As of today (Saturday, 1 October) this seems […]
In: Facilities, Incidents · Tagged with: artisan plumbing and heating, ecotec, equipment repair, plumbing, strataco management
Construction budget passed
Now that the construction budget has been passed and much of the control of the project has been given to project manager John Williamson, I’m actually feeling a little more confident about how things will progress from here on. If nothing else, he has committed to monthly reports, so at least we’ll know what’s going […]
In: Construction · Tagged with: building repair, john williamson inc., strataco management